Steel Pipe Design
Mokelumne Aqueduct No. 1
East Bay Municipal Utility District (Owners)
Progect Manager and Lead Designer of Special 36-inch Diameter Reinforced Steel Manhole Access Ports and Eccentric Reducers for Existing 66-inch and 69-inch Steel Water Transmission Pipelines Within EBMUD's System.
Olivenhain Water Transmission Pipelines
SDCWA and Olivenhain Municipal Water District (Owners):
Project Manager and Lead Designer for Preliminary Design of Two High Pressure, Parallel 78-inch and 48-inch Welded Steel Bi-Directional Pipelines Connecting the Oliverhain Reservoir with the SDCWA's 2nd Aqueduct 108-inch Pipeline No. 5.
San Vicente Water Transmission Pipeline
San Diego County Water Authority (Owner):
102-inch Welded Steel Pressure Water Pipelines to and from a Buried Prestressed Concrete Surge Control Facility. Completed Preliminary Design, System Hydraulics and Surge Control Alternatives Analyses.
14-Mile Long Groundwater Replenishment Pipeline
Orange County Sanitation and Water Districts (Owners):
Project Manager for Preliminary Design of a 14-Mile, $ 60 Million WSP 78"-60" Pressure "Groundwater Replenishment Pipeline" Conveying MF/RO/UV Treated Title 22 Advanced Treated Water Along the Santa Ana River Upstream Within a River Levee, Through a Golf Course, Under Five (5) Interstate Highways and Into Existing Recharge Basins.
State Route 76 High Pressure Water Pipeline Extension Project
Rainbow Municipal Water District (Owner):
Project Manager and Lead Designer for the 16-inch and 12-inch High Pressure (250 PSI) Welded Steel Potable Water Pipeline Designed to be Installed Through the Longitudinal Cells of a New State Route 76 Overcrossing Structure Over Interstate 15 near Fallbrook, California. The work Included the Installation of Seismic Valves on Each Side of the New Overcrossing's Abutment Walls, Concrete Support Blocks That Allowed Longidutidal Movement of the Pipe Casing and Specialized Designs to Counter Pipeline Creep from Vibrations Due to Traffic Passing Overhead on the New Overcrossing Roadway Deck.
Tolt River 120 mgd Design-Build-Operate Water Treatment Plant
Seattle Water Utilities (Owner):
Lead Designer for DBO Team for Several Large Diameter 90"/87"/84"/66" Welded Steel Plant Site Pipelines, Meter Structures and Valve Vault Structures. worked Directly With WTP Design Staff and Contractor in Completing Design While Projects Was Under Construction.
